As I pulled into the parking lot this morning things were in a flurry of busy activity. Many workers were there doing various jobs...outside of the building trim was being added, sidewalks poured and smoothed, trenches being dug, and forms being laid for more concrete. Furniture was being moved into the building, basketball backboards had been hung, sub-flooring was being laid for the gym floor. Take a look at what is still moving along very fast and ahead of schedule.
|
Sacrament table |
|
Basketball Backboards are installed |
|
Pulpit waiting to be installed |
|
Railing for inside chapel |
|
Installing ceiling tiles |
|
Storage Space |
|
Kitchen opens into multipurpose room...nice! |
|
"Carpet Wainscotting" Tough Protection for Walls against errant chairs and feet. |